North Sea Asset Campaign

about this project
This transformation project took place on a major North Sea asset and focused on optimising a 5-month offshore campaign through the deployment of Lean and Agile tools, which included 3 months preparatory work. The client sought to build on previous years’ success and drive even greater operational efficiency, safety, and productivity across multiple contractors and work scopes.
PBI supported the campaign with on-the-ground coaching from the readiness phase through to execution. A campaign room and daily huddle routines were introduced, enabling multi-level visibility and improved interface management. Key interventions included two major Kaizen events focused on critical scopes: a gas turbine installation and seawater lift pump replacement.
The objective was to return time, reduce risk, and enable safe acceleration of activity. Teams applied value stream mapping, set-up reduction, and continuous improvement principles - resulting in 57,000 staff hours returned and £39.8M in OPEX and CAPEX savings over 36 months. These outcomes were driven by internal leadership capability, empowered teams, and an embedded culture of performance improvement.
Key Project Summary "At a glance"
Project Scope
Project Approach take for readiness phase and full Campaign duration:
- Scope: All areas
- Deployment: 8 Months
- Scheduled Hours 78,826
- Client + 3 key Contractors
- Construction
- Commissioning
- Fabric Maintenance
- Phases
- Readiness
- Execution
Improvement Strategy
- Lean & Agile tools
- Campaign Room: all areas & contractors represented
- Huddle Boards: deployed for key areas and scopes
- Kaizen events:
- Sea Water Lift Pump (SWLP)
- Gas Turbine (GT)
- Fabric Maintenance:
- Value Stream Map
- Kanban board
Benefits Delivered
All Campaign Goals Exceeded:
- HSE zero reportable injuries
- Additional +19k hrs achieved, a 24% increase on plan
- £39.8M in OPEX and CAPEX savings over 36 months
- Cumulative Productivity highest on record at 1.04
- Kaizen SWLP: 20% Reduction on scheduled time. Installed additional pump
- Kaizen Gas Turbine: 6 weeks, 3 days removed from plan
- Finished 10 days early